Contents
1.4                        
Summary of Construction Works 
1.5                        
Summary of EM&A Programme
Requirements
1.6 Status of Statutory Environmental Compliance with the Environmental Permit
1.7                        
Status of Other Statutory
Environmental Requirements     
2                            
EM&A Results
for Tung Chung East                         
2.4 Compensation Woodland Monitoring
2.5 Preserved/Transplanted Plant Species of Conservation Importance Monitoring
2.7 Soft Shore Ecological Monitoring
2.10 Landscape and Visual Monitoring
2.11 Implementation Status of Environmental Mitigation Measures
2.12 Summary of Exceedances of the Environmental Quality Performance Liimit
2.13 Summary of Complaints, Notification of Summons and Successful Prosecutions
3.1 Construction Programme for the Coming Month
3.2 Monitoring Schedule for the Coming Month
4                            
Conclusion and
Recommendation                          
 
Annexes
 
Annex B  Environmental Mitigation Implementation
Schedule
Annex C  Status of Submissions and Implementation Status of
Mitigation Measures under EP 
Annex D  Status of Statutory Environmental
Requirements
Annex E 
Air Quality
Annex E1 Calibration Certificates
Annex E2 Monitoring Schedule
Annex E3 Monitoring Results
Annex E4 Event and Action Plan
Annex
F   Noise
Annex F1 Calibration Certificates
Annex F2 Monitoring Schedule
Annex F3 Monitoring Results
Annex F4 Event and Action Plan
Annex G 
Water Quality
Annex G1 Calibration Certificates
Annex G2 Monitoring Schedule
Annex G3 Monitoring Results
Annex G4 Event and Action Plan
Annex H Compensation Woodland Monitoring
Annex I   Preserved/Transplanted Plant
Species of Conservation Importance Monitoring
Annex J   Eco-shoreline Monitoring
Annex K 
Soft Shore Ecology
Annex K3        
Event and Action Plan
Annex L  Landscape and Visual
Monitoring
Annex L1        
Examples of Landscape and Visual Mitigation Measures
Annex L2        
Event and Action Plan
Annex N  Monitoring
Schedule for the Next Reporting Period
| 
   C&D  | 
  
   Construction
  and Demolition  | 
 
| 
   CAP  | 
  
   Contamination
  Assessment Plan  | 
 
| 
   CEDD  | 
  
   Civil
  Engineering and Development Department  | 
 
| 
   CWD  | 
  
   Chinese
  White Dolphin  | 
 
| 
   DCM  | 
  
   Deep
  Cement Mixing  | 
 
| 
   DO  | 
  
   Dissolved
  Oxygen  | 
 
| 
   EIA  | 
  
   Environmental
  Impact Assessment  | 
 
| 
   EIAO  | 
  
   Environmental
  Impact Assessment Ordinance  | 
 
| 
   EIS  | 
  
   Ecologically
  Important Stream  | 
 
| 
   EM&A  | 
  
   Environmental
  Monitoring and Audit  | 
 
| 
   EP  | 
  
   Environmental
  Permit  | 
 
| 
   EPD  | 
  
   Environmental
  Protection Department  | 
 
| 
   ER  | 
  
   Engineer's
  Representative  | 
 
| 
   ERM  | 
  
   ERM-Hong
  Kong, Limited  | 
 
| 
   ET  | 
  
   Environmental
  Team  | 
 
| 
   HVS  | 
  
   High
  Volume Sampler  | 
 
| 
   IEC  | 
  
   Independent
  Environmental Checker  | 
 
| 
   PDA  | 
  
   Planned
  Development Area  | 
 
| 
   PME  | 
  
   Powered
  Mechanical Equipment   | 
 
| 
   QPME  | 
  
   Quality
  Powered Mechanical Equipment   | 
 
| 
   RAP  | 
  
   Remediation
  Action Plan  | 
 
| 
   RR  | 
  
   Remediation
  Report  | 
 
| 
   RTTM  | 
  
   Real
  Time Tracking and Monitoring  | 
 
| 
   SS  | 
  
   Suspended
  Solid  | 
 
| 
   TCB  | 
  
   Tung
  Chung Bay  | 
 
| 
   TCE  | 
  
   Tung
  Chung East  | 
 
| 
   TCNTE  | 
  
   Tung
  Chung New Town Extension   | 
 
| 
   TCW  | 
  
   Tung
  Chung West  | 
 
| 
   The
  Project  | 
  
   Tung
  Chung New Town Extension (East)  | 
 
| 
   THW  | 
  
   Tai
  Ho Wan  | 
 
| 
   TSP  | 
  
   Total
  Suspended Particulate  | 
 
| 
   Updated
  EM&A Manual  | 
  
   Updated Environmental Monitoring and
  Audit Manual for Tung Chung New Town Extension prepared by ERM under
  Agreement No. CE 60/2017 (EP) and deposited to EPD under Environmental Permit
  No. EP-519/2016  | 
 
 
Tung Chung New Town Extension
(TCNTE) is one of the major initiatives under the Government's multi-pronged
approach to increase land supply to meet Hong Kong's medium- to long-term needs
for housing, economic and social developments.  The Environmental Impact
Assessment (EIA) Report for TCNTE (Register No. AEIAR-196/2016) was approved on
8 April 2016 and the Environmental Permit (EP) No. EP-519/2016, covering the
construction and operation of TCNTE, was granted on 9 August 2016. The EIA
Report and EP cover both Tung Chung East (TCE) and Tung Chung West (TCW). 
ERM-Hong Kong, Limited (ERM) is commissioned to undertake the role of
Environmental Team (ET) for the construction and operation of TCE Project (“the
Project”) in accordance with the requirements specified in the EP, Updated
Environmental Monitoring and Audit (EM&A) Manual, EIA Report of the TCNTE
project and other relevant statutory requirements.  
The construction of the Contract
No. NL/2017/03 - Tung Chung New Town Extension –
Reclamation and Advance Works (“Contract 1”) at TCE commenced on 9 July
2018. 
The construction of the Contract
No. NL/2020/02 - Tung Chung New Town Extension – Salt Water
Supply System (“Contract 2”) at TCE commenced on 4 September 2021.
The construction of the Contract
No. NL/2020/03 - Tung Chung New Town Extension – Major Infrastructure Works in
Tung Chung East (“Contract 3”) at TCE commenced on 5 November 2021.
The construction of the Contract
No. NL/2020/07 - Tung Chung New Town Extension – Tai Ho Interchange (“Contract
7”) at TCE commenced on 15 March 2022.
This
is the Monthly EM&A report presenting the EM&A works carried out during
the period from 1 to 31 March 2023 for the TCE Project in accordance with the
Updated EM&A Manual.  
A
summary of monitoring and audit activities conducted in the reporting period is
listed below:
Air Quality
Monitoring                           
5 sessions
Noise
Monitoring                                    
5 sessions
Water Quality
Monitoring                      
14 sessions
Preserved Plant
Species Monitoring        1 session
Soft Shore
Ecological Monitoring
           1 session
 Environmental
Site Inspection 
-         
Contract
1       
         
                  
5 sessions
-         
Contract
2                                    
5 sessions
-         
Contract
3                                    
5 sessions
-         
Contract
7                                    
4 sessions
Environmental
Management Meeting
-         
Contract
1                                    
1 session
-         
Contract
2                                    
1 session
-         
Contract
3                                    
1 session
-         
Contract
7                                    
1 session  
Environmental
auditing works, including weekly site inspections of construction works
conducted by the ET, audit of works vessels, audit of implementation of
Complaint Management Plan, Dolphin Watching Plan, Works Vessel Travel Route
Plan, Silt Curtain Deployment Plan, Spill Response Plan, Detailed
Preservation and/or Translocation of Plant Species of Conservation Importance,
Detailed Compensatory Woodland Planting Plan and
Waste Management Plan were conducted in the reporting period.  Based on
the audit results and the observation for the reporting period, environmental
pollution control and mitigation measures for the Project were properly
implemented.
Breaches
of Action and Limit Levels for Air Quality
No
exceedance of Action and Limit Levels was recorded for construction air quality
monitoring in the reporting period. 
Breaches of Action and Limit Levels for
Noise
No exceedance of Action
and Limit Levels was recorded for construction noise monitoring in the
reporting period.
Breaches
of Action and Limit Levels for Water Quality
Suspended
Solids (SS) exceedance was recorded during the reporting period.  Relevant
investigation and follow-up actions were conducted according to the EM&A programme.  The exceedance was considered not related
to this Project after investigation. 
Eco-shoreline
Monitoring
Mangrove
eco-shoreline and rocky eco-shoreline are under construction while the
construction of vertical eco-shoreline has been substantially completed.
Soft
Shore Ecological Monitoring
Based
on the impact monitoring conducted during the reporting period, there was no
evidence showing any significant difference in intertidal communities when
compared against the data obtained during baseline monitoring.  The ET
will continue to observe the change in density or the distribution pattern of
horseshoe crab, seagrass and intertidal soft shore communities taking into account natural fluctuation in respect of the
occurrence and distribution pattern.
Environmental
Complaints, Non-compliance & Summons
There
was no notification of summons or prosecution recorded in the reporting period.
One
(1) environmental complaint related to Contract 1 was received in the reporting
period.  Investigation was conducted for the environmental complaint in
accordance with the complaint handling process as stated in the Complaint
Management Plan.
Reporting
Change
There was no reporting change in the reporting period. 
Key
Issues For The Coming Month
Potential environmental impacts arising
from the upcoming construction activities in the next reporting period of April
2023 are mainly associated with dust emission, noise from barge and plant
operation during normal working hours and restricted hours, elevation in SS due
to marine filling works, disturbance to Chinese White Dolphin (CWD) during
marine works, handling and storage of C&D materials generated from
construction activities, efficiency of wastewater and drainage management and
tree protection.  The ET will keep track on the construction works to
confirm compliance of environmental requirements and the proper implementation
of all necessary mitigation measures.  The ET will also recommend to the
Contractor about the environmental toolbox topics on the abovementioned key
issues for the coming month.
 
Tung Chung New Town Extension
(TCNTE) is one of the major initiatives under the Government's multi-pronged
approach to increase land supply to meet Hong Kong's medium- to long-term needs
for housing, economic and social developments. The Environmental Impact
Assessment (EIA) Report for TCNTE (Register No. AEIAR-196/2016) was approved on
8 April 2016 and the Environmental Permit (EP) No. EP-519/2016, covering the
construction and operation of TCNTE, was granted on 9 August 2016. The EIA
Report and EP cover both Tung Chung East (TCE) and Tung Chung West (TCW).
ERM-Hong Kong, Limited (ERM) is
commissioned to undertake the role of Environmental Team (ET) for the
construction and operation of TCE Project (“the Project”) in accordance with
the requirements specified in the EP, Updated Environmental Monitoring and
Audit (EM&A) Manual ([1]),
EIA Report of the TCNTE project ([2])
and other relevant statutory requirements.
The TCNTE comprises the following
elements:
(a)     TCE
Project
1.          
Reclamation of the seabed by a non-dredged method at
TCE to form a total of about 130 hectares of land;
2.          
Construction of about 4.9 kilometers
of seawalls, with an eco-shoreline, three drainage box culvert outfalls, three
circulation drains and a seawater intake at TCE;
3.          
Provision of infrastructure for Tung Chung Area 58,
including construction of a single two-lane road with a footpath and the
associated utility works;
4.          
Construction of proposed open space;
5.          
Construction of roads, footpaths, cycle tracks and the
associated junction / road improvement works;
6.          
Engineering infrastructure works covering drainage,
sewerage, waterworks (including a fresh water service
reservoir, a salt water service reservoir and a salt water pumping station),
common utility tunnels and landscaping works; and
7.          
Implementation of environmental mitigation measures
and environmental monitoring and audit programme for the works.
(b)     TCW
Project
1.          
Site formation works at TCW;
2.          
Construction of proposed open space;
3.          
Construction of the River Park including a visitor
centre at TCW; and
4.          
Construction of sustainable urban drainage systems at
TCW.
The locations of Contracts 1, 2, 3 and 7 are shown in Figure 1.1
to 1.4.  The construction and the reclamation
related marine works of Contract 1 commenced on 9 and 13 July 2018,
respectively.  The construction of Contracts 2, 3 and 7 commenced on 4
September 2021, 5 November 2021 and 15 March 2022, respectively.
This
is the Monthly EM&A Report for the TCE Project which summarises
the key findings of the EM&A programme during the
reporting period from 1 to 31 March 2023 for the construction works.
The
organization structure of the Project is shown in Annex A.  The key
personnel contact names and contact details are summarized in Table 1.1
below.
Table
1.1         Contact Information of Key
Personnel
| 
   Party  | 
  
   Position  | 
  
   Name  | 
  
   Telephone  | 
 
| 
   Environmental
  Team (ET)  (ERM-Hong
  Kong, Limited)  | 
  
   ET
  Leader  | 
  
   Kelvin
  So  | 
  
   3894
  9504  | 
 
| 
   Deputy
  ET Leader Deputy
  ET Leader  | 
  
   Raymond
  Chow Candy
  Wong  | 
  
   3894
  9509 3894
  9508  | 
 |
| 
      | 
  
      | 
  
      | 
  
      | 
 
| 
   Independent Environmental Checker
  (IEC) (Binnies Hong
  Kong Limited)  | 
  
   IEC  | 
  
   Manuel
  Chua  | 
  
   3894 9807  | 
 
| 
   Deputy
  IEC    | 
  
   Edward
  Lau  | 
  
   3894
  9695  | 
 |
| 
      | 
 |||
| 
   Contract No.
  NL/2017/03 - Tung Chung New Town Extension –
  Reclamation and Advance Works (Contract 1)  | 
 |||
| 
   Civil
  Engineering and Development Department      | 
  
   Senior
  Geotechnical Engineer    | 
  
   C
  H Yan  | 
  
   3894
  9702  | 
 
| 
   Marine
  Conservation Officer    | 
  
   Wo
  King Tai  | 
  
   3894
  9707   | 
 |
| 
   Engineer’s
  Representative  (ER)
   (AECOM
  Asia Company Limited)    | 
  
   Principal
  Resident Engineer Chief
  Resident Engineer Senior
  Resident Engineer Senior
  Resident Engineer  | 
  
   Frankie
  Fan   Chris
  Cheung   Chris
  Chow   Edwin
  Fu  | 
  
   3894
  9603   3894
  9604   3894 9651   3894 9644  | 
 
| 
   Resident
  Engineer  | 
  
   Nelson
  Ling  | 
  
   3894
  9647  | 
 |
| 
   Senior
  Inspector of Works    | 
  
   C
  K Liu  | 
  
   3894
  9733  | 
 |
| 
   Contractor
   (Build
  King – SCT Joint Venture)    | 
  
   Site
  Agent  | 
  
   David
  Wong  | 
  
   9653
  8635  | 
 
| 
   Civil
  Division Head  | 
  
   Marco
  Chan  | 
  
   9257
  7033  | 
 |
| 
   Environmental
  Officer  | 
  
   Issac Wong  | 
  
   9873 8968  | 
 |
| 
   24-hour
  Complaint Hotline  | 
  
   -  | 
  
   5976
  1853  | 
 |
| 
      | 
  
      | 
  
      | 
  
      | 
 
| 
   Contract No.
  NL/2020/02 - Tung Chung New Town Extension – Salt Water
  Supply System (Contract
  2)  | 
 |||
| 
   Civil
  Engineering and Development Department    | 
  
   Senior
  Engineer  | 
  
   Patrick
  C Y Yeung  | 
  
   2231
  4435  | 
 
| 
   Electrical
  & Mechanical Engineer    | 
  
   Samson
  K L Yip  | 
  
   2231
  4460   | 
 |
| 
   Engineer’s
  Representative  (ER)
   (AECOM
  Asia Company Limited)    | 
  
   Principal
  Resident Engineer Senior
  Resident Engineer  | 
  
   Frankie
  Fan   Sunny
  Ng  | 
  
   3894
  9603   3894
  9605  | 
 
| 
   Senior
  Resident Engineer  | 
  
   Vincent
  Leung  | 
  
   3894
  9645  | 
 |
| 
   Resident
  Engineer  | 
  
   Terence
  Chan  | 
  
   3894
  9683  | 
 |
| 
   Senior
  Inspector of Works    | 
  
   Wong
  Ting Yu  | 
  
   3894
  9706  | 
 |
| 
   Contractor
   (China
  Geo-Engineering Corporation)    | 
  
   Construction
  Manager  | 
  
   Ambrose
  Kwong  | 
  
   6198
  7787  | 
 
| 
   Site
  Agent  | 
  
   Timothy
  Lo  | 
  
   9661
  2662  | 
 |
| 
   Construction
  Team Leader  | 
  
   Aaren Li  | 
  
   6468
  8138  | 
 |
| 
   Environmental
  Officer  | 
  
   Aaren Li  | 
  
   6468
  8138  | 
 |
| 
      | 
  
   24-hour
  Complaint Hotline  | 
  
   -  | 
  
   5976
  1853  | 
 
| 
      | 
  
      | 
  
      | 
  
      | 
 
| 
   Contract No.
  NL/2020/03 - Tung Chung New Town Extension – Major Infrastructure Works in
  Tung Chung East (Contract
  3)  | 
 |||
| 
   Civil
  Engineering and Development Department    | 
  
   Senior
  Engineer  | 
  
   Eddie
  W C Lam  | 
  
   2231
  4445  | 
 
| 
   Senior
  Engineer  | 
  
   Phoebe
  Tang  | 
  
   2231
  4423  | 
 |
| 
   Engineer  | 
  
   Timothy
  H M Chan  | 
  
   2231
  4473   | 
 |
| 
   Engineer  | 
  
   Colin
  K C Wong  | 
  
   2231
  4417  | 
 |
| 
   Engineer  | 
  
   Wing
  Chen  | 
  
   3894
  9704  | 
 |
| 
      | 
  
      | 
  
      | 
  
      | 
 
| 
   Engineer’s
  Representative  (ER)
   (AECOM
  Asia Company Limited)    | 
  
   Principal
  Resident Engineer  | 
  
   Frankie
  Fan    | 
  
   3894
  9603    | 
 
| 
   Chief
  Resident Engineer  | 
  
   Gloria
  Tang  | 
  
   3894
  9639  | 
 |
| 
   Senior
  Resident Engineer  | 
  
   Edwin
  Fu  | 
  
   3894
  9644  | 
 |
| 
   Resident
  Engineer  | 
  
   David
  Li  | 
  
   3894
  9684  | 
 |
| 
      | 
  
   Resident
  Engineer  | 
  
   Carl
  Yu  | 
  
   3894
  9671  | 
 
| 
      | 
  
   Senior
  Inspector of Works  | 
  
   Douglas
  Ng  | 
  
   3894
  9737  | 
 
| 
   Contractor
   (Build
  King Civil Engineering Limited)    | 
  
   Construction
  Manager  | 
  
   Cheung
  Siu Lun  | 
  
   2272
  3680  | 
 
| 
   Site
  Agent  | 
  
   Paul
  Lui  | 
  
   9095
  7922  | 
 |
| 
   Deputy
  Site Agent  | 
  
   Aldous
  Lo  | 
  
   9225
  0368  | 
 |
| 
   Construction
  Team Leader  | 
  
   Ken
  Yau  | 
  
   9197
  2219  | 
 |
| 
   Environmental
  Officer  | 
  
   Allen
  Wong  | 
  
   6012 2643  | 
 |
| 
      | 
  
   24-hour
  Complaint Hotline  | 
  
   -  | 
  
   5976
  1853  | 
 
| 
      | 
  
      | 
  
      | 
  
      | 
 
| 
   Contract
  No. NL/2020/07 - Tung Chung New Town Extension – Tai Ho Interchange (Contract 7)  | 
 |||
| 
   Civil
  Engineering and Development Department  | 
  
   Senior
  Engineer  | 
  
   Phoebe
  Tang  | 
  
   2231
  4423  | 
 
| 
   Engineer  | 
  
   Matthew
  Ng  | 
  
   2231
  4449  | 
 |
| 
      | 
  
      | 
  
      | 
 |
| 
      | 
  
      | 
  
      | 
  
      | 
 
| 
   Engineer’s
  Representative  (ER)
   (AECOM
  Asia Company Limited)  | 
  
   Principal
  Resident Engineer    | 
  
   Frankie
  Fan    | 
  
   3894
  9603  | 
 
| 
   Senior
  Resident Engineer  | 
  
   Kelvin
  Kwan  | 
  
   3894
  9641  | 
 |
| 
   Senior
  Resident Engineer  | 
  
   Brian
  Li  | 
  
   3894
  9556  | 
 |
| 
   Resident
  Engineer  | 
  
   Kingsley
  Ho  | 
  
   3894
  9552  | 
 |
| 
   Resident
  Engineer  | 
  
   Carl
  Yu  | 
  
   3894
  9671  | 
 |
| 
   Senior
  Inspector of Works    | 
  
   Douglas
  Ng  | 
  
   3894
  9554  | 
 |
| 
   Contractor
   (Build
  King Civil Engineering Limited)  | 
  
   Site
  Agent  | 
  
   Hon
  Yee  | 
  
   9090
  3109  | 
 
| 
   Deputy
  Site Agent  | 
  
   Vincent
  Kwan  | 
  
   9833
  1313  | 
 |
| 
   Construction
  Team Leader  | 
  
   Vincent
  Lo  | 
  
   9883
  9229  | 
 |
| 
   Environmental
  Officer  | 
  
   Nash Wong  | 
  
   9810
  1946  | 
 |
| 
   24-hour
  Complaint Hotline  | 
  
   -  | 
  
   5976
  1853  | 
 |
| 
      | 
  
      | 
  
      | 
  
      | 
 
As informed by the Contractor, details
of the major works carried out in this reporting period are listed below:
Table
1.2         Major Activities in the
Reporting Period
| 
   Activities  | 
  
   Key Issues  | 
  
   Key Mitigation Measures  | 
 
| 
   Contract
  No. NL/2017/03 - Tung Chung New Town Extension –
  Reclamation and Advance Works (Contract 1)  | 
 ||
| 
   Land-based Works  | 
  
      | 
  
      | 
 
| 
   ·        
  Ground
  investigation works ·        
  Placing
  of sorted public fill ·        
  Box
  culvert construction ·        
  Mangrove
  planting  | 
  
   ·        
  Dust emission ·        
  Handling and storage of
  C&D materials generated from construction activities
   ·        
  Noise from plant
  operation ·        
  Emission of dark smoke
  from PMEs ·        
  Efficiency of wastewater
  and drainage management   | 
  
   ·        
  Good site practices ·        
  Regular water spraying on
  stockpiles, unpaved haul road and land filling area ·        
  Provide tarpaulin sheets
  coverage on stockpiles ·        
  Sorting and reuse of
  C&D materials as far as practicable ·        
  Use of QPME and noise
  barrier/acoustic mat ·        
  Regular maintenance of
  PMEs ·        
  Implementation of
  wastewater and drainage management  | 
 
| 
   Marine-based Works  | 
  
      | 
  
      | 
 
| 
   ·        
  Laying
  of geotextile for seawall construction ·        
  Seawall
  construction (including vertical seawall, sloping seawall &
  eco-shoreline)  | 
  
   ·        
  Elevation in impact on
  Water Quality due to sediment loss from sand blanket laying and marine
  filling works ·        
  Potential surface runoff ·        
  Potential filling
  material drop from barges ·        
  Disturbance to Chinese
  White Dolphin ·        
  Noise from marine vessels
  and plant operation during normal working hours or restricted hours ·        
  Dust emission during
  storage and transfer of sand/ sorted public fill  ·        
  Emission of dark smoke
  from marine vessel      | 
  
   ·        
  Provision of perimeter
  silt curtain  ·        
  Provision of a leading
  seawall of at least 200m before marine filling works ·        
  Regular cleaning of
  accumulated sand/fill materials at the edge of the barges ·        
  Implementation of Dolphin
  Watching for the marine-based works ·        
  Strictly follow
  requirement under CNP for the use of PMEs and works within restricted period  ·        
  Use of acoustic mat and
  other noise mitigation measures when necessary ·        
  Regular maintenance of
  engines and mechanical equipment    | 
 
 
| 
   Contract
  No. NL/2020/02 - Tung Chung New Town Extension – Salt Water
  Supply System (Contract
  2)  | 
 ||
| 
   Land-based Works  | 
  
      | 
  
      | 
 
| 
   ·        
  RC structure of pumping
  station Construction at Portion 6 ·        
  Construction of service
  reservoir and deflector wall, soil nailing works and ground investigation
  works for deflector wall and rigid barrier at Portion 3 ·        
  Remedial works for frac
  out and construction of mud pit 2 for HDD works at Portion 3 ·        
  Watermain laying works at
  Portion 3 along Yu Tung Road ·        
  Sheet piling and
  excavation works for ELS for pipe jacking at Portion 3 ·        
  Watermain laying works
  and ELS for drainage works at Yi Tung Road at Portion 5 ·        
  Trench excavation,
  manhole construction and pipe laying for drainage works at Portion 5A ·        
  Fabrication works at box
  culvert at Portion 5B ·        
  Establishment works for
  the compensatory planting at Portion 1 and 2  | 
  
   ·        
  Dust emission ·        
  Handling and storage of
  C&D materials generated from construction activities
   ·        
  Noise from plant
  operation ·        
  Emission of dark smoke
  from PMEs ·        
  Efficiency of wastewater
  and drainage management ·        
  Tree protection   | 
  
   ·        
  Good site practices ·        
  Regular water spraying on
  stockpiles, unpaved haul road and land filling area ·        
  Provide tarpaulin sheets
  coverage on stockpiles ·        
  Sorting and reuse of
  C&D materials as far as practicable ·        
  Use of QPME and noise
  barrier/acoustic mat ·        
  Regular maintenance of
  PMEs ·        
  Implementation of
  wastewater and drainage management ·        
  Retain and protect all
  existing trees and vegetation within the study area which are not directly
  affected by the works    | 
 
| 
        | 
 ||
| 
   Contract
  No. NL/2020/03 - Tung Chung New Town Extension – Major Infrastructure Works
  in Tung Chung East (Contract
  3)  | 
 ||
| 
   Land-based Works  | 
  
      | 
  
      | 
 
| 
   ·        
  Excavation and ELS works
  at Portion 104 ·        
  Excavation and ELS works
  at CUT no.1,2 & 3 and supporting building ·        
  Construction works for
  CUT no. 1 structure ·        
  Construction works and
  furniture installation of PM office at WA9 ·        
  Construction works of
  Contractor office at WA6 ·        
  Drainage, Sewerage and
  watermain works at Road L4, L3 and L5 ·        
  DCS works at Road L4 and
  L3. ·        
  Pipe laying works for
  twin rising mains/ watermain laying at Man Tung Road ·        
  Preparation works for
  pipe jacking works at Ying Tung Road ·        
  Preparation works for
  pipe jacking at Yi Tung Road ·        
  Foundation works for
  noise barrier at Portion 11 ·        
  Road widening works at
  Ying Hei Road  | 
  
   ·        
  Dust emission ·        
  Handling and storage of
  C&D materials generated from construction activities
   ·        
  Noise from plant
  operation ·        
  Emission of dark smoke
  from PMEs ·        
  Efficiency of wastewater
  and drainage management    | 
  
   ·        
  Good site practices ·        
  Regular water spraying on
  stockpiles, unpaved haul road and land filling area ·        
  Provide tarpaulin sheets
  coverage on stockpiles ·        
  Sorting and reuse of
  C&D materials as far as practicable ·        
  Use of QPME and noise
  barrier/acoustic mat ·        
  Regular maintenance of
  PMEs ·        
  Implementation of
  wastewater and drainage management    | 
 
 
| 
   Contract
  No. NL/2020/07 - Tung Chung New Town Extension – Tai Ho Interchange (Contract 7)  | 
 ||
| 
   Land-based Works  | 
 ||
| 
   ·        
  Open cut excavation and
  pipe laying for rising main and watermain at Portion 146-5 to 146-9 ·        
  Trench excavation and
  pipe laying works at Portions 32 (Sham Shui Kok
  Drive), Portion 34 Phase 1 and Portions 36-38 ·        
  Pipe pile installation,
  trench excavation and pipe laying works at Portion 32 (Access Road adjacent
  to MTRC Siu Ho Wan Depot) ·        
  WSD Subway DN200
  diversion and DN1200 installation at Portion 35 ·        
  ELS for construction of
  retaining walls FR1 ·        
  ELS works for Pak Mong Subway Extension Phase 1 ·        
  Piling works for Pak Mong Channel Bridge ·        
  G.I. works for retaining
  wall Wall D&E ·        
  Tree felling works at
  Portions 30 and 33 ·        
  Temporary working
  platform at abutment A1b ·        
  Sheetpiling at Casting Yard A2 ·        
  Temporary site office
  construction at Portion 31 Site clearance and
  tidiness      | 
  
   ·        
  Dust emission ·        
  Handling and storage of
  C&D materials generated from construction activities
   ·        
  Noise from plant
  operation ·        
  Emission of dark smoke
  from PMEs ·        
  Efficiency of wastewater
  and drainage management ·        
  Tree protection  | 
  
   ·        
  Good site practices ·        
  Regular water spraying on
  stockpiles, unpaved haul road and land filling area ·        
  Provide tarpaulin sheets
  coverage on stockpiles ·        
  Sorting and reuse of
  C&D materials as far as practicable ·        
  Use of QPME and noise
  barrier/acoustic mat ·        
  Regular maintenance of
  PMEs ·        
  Implementation of
  wastewater and drainage management ·        
  Retain and protect all
  existing trees and vegetation within the study area which are not directly
  affected by the works  | 
 
The environmental
mitigation implementation schedule is presented in Annex B.
The
status for all environmental aspects are presented in Table
1.3.  The EM&A requirements remained unchanged during the
reporting period.
 
Table
1.3         Summary of Status for the
Environmental Aspects under the Updated EM&A Manual
| 
    Parameters  | 
   
    Status  | 
  
| 
   Air
  Quality  | 
 |
| 
   Baseline
  Monitoring  | 
  
   The
  results of baseline air quality monitoring for TCE were reported in Baseline
  Monitoring Report and submitted to EPD under EP Condition 3.4    | 
 
| 
   Impact
  Monitoring  | 
  
   On-going
  for TCE, monitoring conducted three times every six days  | 
 
| 
      | 
  
      | 
 
| 
   Noise  | 
 |
| 
   Baseline
  Monitoring  | 
  
   The
  results of baseline noise monitoring for TCE were reported in Baseline
  Monitoring Report and submitted to EPD under EP Condition 3.4    | 
 
| 
   Impact
  Monitoring  | 
  
   On-going
  for TCE, monitoring conducted once per week    | 
 
| 
   Impact
  Monitoring for Road Traffic Noise during Operational Phase    | 
  
   To
  be conducted during operational phase  | 
 
| 
   Fixed
  Noise Commissioning Test  | 
  
   To
  be implemented by the Contractor before operation of TCNTE  | 
 
| 
      | 
  
      | 
 
| 
   Water
  Quality  | 
 |
| 
   Baseline
  Monitoring  | 
  
   The
  results of baseline water quality monitoring for TCE were reported in
  Baseline Monitoring Report and submitted to EPD under EP Condition 3.4    | 
 
| 
   Impact
  Monitoring  | 
  
   On-going
  for TCE, monitoring conducted three times per week  | 
 
| 
      | 
  
      | 
 
| 
   Waste
  Management  | 
 |
| 
   Waste
  Monitoring  | 
  
   On-going  | 
 
| 
      | 
  
      | 
 
| 
   Land
  Contamination   | 
 |
| 
   Contamination
  Assessment Plan (CAP), Remediation Action Plan (RAP) and Remediation Report
  (RR)  | 
  
   To
  be conducted under TCW. Refer to the EM&A Reports of TCW.  | 
 
| 
      | 
  
      | 
 
| 
   Ecology  | 
 |
| 
   Monitoring
  for Compensation Woodland    | 
  
   Compensation
  Woodland Planting was completed on 30 September 2022.  Monitoring for
  Compensation Woodland will be carried out subject to the approval from EPD on
  the monitoring proposal.    | 
 
| 
   Monitoring
  for Emergent Plant inside the future River Park    | 
  
   To
  be conducted under TCW. Refer to the EM&A Reports of TCW.  | 
 
| 
   Monitoring
  for Translocated Amphibians of Conservation Importance    | 
  
   To
  be conducted under TCW. Refer to the EM&A Reports of TCW.  | 
 
| 
   Monitoring
  for Preserved/Transplanted Plant Species of Conservation Importance    | 
  
   On-going,
  for transplanted plant species, transplantation works was carried out on 21
  January 2022 and monitoring conducted once per week for the first three
  months; for preserved plant species, monitoring conducted once per month     | 
 
| 
   Monitoring
  for Tung Chung Stream EIS and Wong Lung Hang EIS    | 
  
   To
  be conducted under TCW. Refer to the EM&A Reports of TCW. 
  Monitoring for Wong Lung Hang was not required and
  the proposal was accepted by EPD on 2 September 2021  | 
 
| 
      | 
  
      | 
 
| 
   Eco-shoreline
  Monitoring  | 
  
   To
  be conducted when eco-shoreline after completion of reclamation works    | 
 
| 
   Tung
  Chung Bay and Tai Ho Wan Baseline Monitoring  | 
  
   The
  results of baseline soft shore ecological monitoring at Tung Chung Bay and
  Tai Ho Wan were reported in Baseline Monitoring Report and submitted to EPD
  under EP Condition 3.4    | 
 
| 
   Tung
  Chung Bay and Tai Ho Wan Impact Monitoring  | 
  
   On-going
  for TCE, monitoring conducted quarterly   | 
 
| 
      | 
  
      | 
 
| 
   Landscape
  and Visual  | 
  
      | 
 
| 
   Baseline
  Monitoring  | 
  
   The
  results of baseline landscape and visual monitoring were reported in Baseline
  Monitoring Report and submitted to EPD under EP Condition 3.4    | 
 
| 
   Impact
  Monitoring  | 
  
   On-going  | 
 
| 
      | 
  
      | 
 
| 
   Site
  Environmental Audit  | 
 |
| 
   Regular
  Site Inspection    | 
  
   On-going  | 
 
| 
   Dolphin
  Watching Plan implementation measures    | 
  
   Under
  implementation by the Contractor of Contract 1  | 
 
| 
   Works
  Vessel Travel Route Plan implementation measures    | 
  
   Under
  implementation by the Contractor of Contract 1  | 
 
| 
   Silt
  Curtain Deployment Plan implementation measures  | 
  
   Under
  implementation by the Contractor of Contract 1  | 
 
| 
      | 
  
      | 
 
| 
   Spill
  Response Plan implementation measures    | 
  
   Under
  implementation by the Contractor of Contract 1  | 
 
| 
   Detailed
  Preservation and/or Translocation Plan for Plant Species of Conservation
  Importance implementation measures    | 
  
   Under
  implementation by the Contractor of Contract 2  | 
 
| 
   Detailed
  Compensatory Woodland Planting Plan implementation measures  | 
  
   Under
  implementation by the Contractor of Contract 2  | 
 
| 
      | 
  
      | 
 
| 
   Waste
  Management Plan implementation measures  | 
  
   Under
  implementation by the Contractor of Contract 1  | 
 
| 
      | 
  
      | 
 
| 
   Complaint
  Hotline and Email Channel  | 
  
   Under
  implementation by the Contractor of Contract 1, 2, 3 and 7  | 
 
| 
      | 
  
      | 
 
| 
   Environmental
  Log Book  | 
  
   On-going  | 
 
Taking into account the construction works, impact
monitoring of air quality, noise, water quality, soft shore ecological
monitoring and waste management were carried out in the reporting period. 
The monitoring schedule of air quality, noise, water quality and soft shore
ecological monitoring are provided in Annex E2, Annex
F2, Annex G2 and Annex K1, respectively.
The
EM&A programme also involved environmental site
inspections and related auditing conducted by the ET for checking the
implementation of the required environmental mitigation measures recommended in
the approved EIA Report and relevant EP submissions, including Complaint
Management Plan, Dolphin Watching Plan, Works Vessel Travel Route Plan, Silt
Curtain Deployment Plan, Spill Response Plan, Detailed Preservation and/or
Translocation Plan for Plant Species of Conservation Importance, Detailed
Compensatory Woodland Planting Plan and Waste Management Plan.  
To
promote the environmental awareness and enhance the environmental performance
of the contractors, environmental trainings and regular environmental
management meetings were conducted during the reporting period, which are
summarized as below:
·       
Four
(4) environmental management committee meetings were held with the Contractors
of Contract 1, 2, 3 and 7 and ER, ET, IEC and CEDD on 16, 15, 22 and 14 March
2023, respectively;
·       
Environmental
toolbox trainings on chemical handling, use of spill kits, operation and
maintenance, waste management and disposal, dark smoke, mosquito control, dust
suppression/waste management , nuisance to residence
(light pollution/sudden noise/dusty work), site hygiene (rubbish, mosquito,
rodent control) on 1, 3, 8, 10, 15, 17, 22, 24 and 29 March 2023 were conducted
for Contract 1;
·       
Environmental
toolbox trainings on Quality Powered Mechanical Equipment (QPME) and proper drainage system /wastewater
treatment and discharge on 14 and 21 March 2023 were conducted for Contract 2;
·       
Environmental
toolbox trainings on cement debagging and mixing, milling, paving, plastering and
painting, environmental abatement facilities, acoustic decoupling measures,
plant and machinery environmental precaution, chemical waste and handling of
chemical spillage and energy saving on 2, 7, 9, 14, 16, 21, 23, 28 and 30 March
2023 were conducted for Contract 3;
·       
Environmental
toolbox trainings on site plant and machinery, maintenance of site access,
boundary and haul roads, protection and preservation of trees, ground investigation
and site clearance on 1, 8, 15, 22 and 29 March 2023 were conducted for
Contract 7.
The
status of statutory environmental compliance with the EP conditions
under the EIAO, submission status under the EP and implementation status of
mitigation measures are presented
in Annex C.  
The
environmental licenses and permits, including environmental permit, discharge
license under Water Pollution Control Ordinance, registration as chemical waste
producer, construction noise permit and specified processes license, which were
valid in the reporting period are presented in Annex D.  No non-compliance with environmental
statutory requirements was recorded.  
The
EM&A programme for the Project required
environmental monitoring for air quality, noise, water quality and marine
ecology as well as environmental site inspections for air quality, noise, water
quality, waste management, marine ecology and landscape and visual
impacts.  The EM&A requirements and related findings for each
component are summarized in the following sections.
According
to the Updated EM&A Manual of the Project, impact air quality monitoring in
terms of 1-hour Total Suspended Particulate (TSP) was conducted three (3) times
every six (6) days when the highest dust impact was expected.  The Action
and Limit Levels of the air quality monitoring is provided in Table 2.1
below. 
Table
2.1         Action and Limit Levels for
1-hour TSP
| 
    Location  | 
   
    Action Level, µg/m3  | 
   
    Limit Level, µg/m3  | 
  
| 
   Monitoring
  station for Tung Chung East  | 
  
   279  | 
  
   500  | 
 
Portable direct reading dust meters
were used to measure 1-hour TSP levels in undertaking the air quality
monitoring for the Project.  The proposed use of portable direct reading
dust meters was submitted to IEC and obtained agreement from the IEC as stated
in Section 5.5 of the Updated EM&A Manual.  With the use of direct
reading dust meter, it can allow prompt and direct results for the EM&A
reporting and the implementation of the event and action plan.  The
portable direct reading dust meter would be calibrated every year against High Volume Sampler (HVS) to
check the validity and      accuracy of the results
measured by direct reading method.
The
monitoring location and equipment used in the impact air quality monitoring programme are summarized in Table 2.2 and
illustrated in Figure 2.1.  Copies of the calibration
certificates for the equipment are presented in Annex E1, which showed that the portable direct reading
dust meter is capable of providing comparable results with that provided by a HVS.
  
Table
2.2         Air Quality Monitoring
Details
| 
    Monitoring Station  | 
   
    Location  | 
   
    Parameter  | 
   
    Frequency and Duration  | 
   
    Monitoring Dates  | 
   
    Equipment  | 
  
| 
   DM-1  | 
  
   Tung
  Chung Area 56 – Ying Tung Estate  | 
  
   1-hour
  TSP  | 
  
   Three
  times per six days during the construction period of the Project  | 
  
   3,
  9, 15, 21 and 27 March 2023  | 
  
   1-hour
  TSP Dust Meter  SIBATA
  LD-3B (S/N: 336338)  | 
 
| 
   Remark:
   It
  should be noted that impact monitoring at other construction dust monitoring
  locations at TCE as stated in the Updated EM&A Manual will commence after
  the flat intake (for Monitoring Stations DM-2, DM-3
  and DM-4).   | 
 |||||
The
schedule for air quality monitoring during the reporting period is provided in Annex E2.
The
monitoring results for 1-hour TSP are summarized in Table 2.3.  The
monitoring data and the graphical presentation are provided in Annex E3.
Table
2.3         Summary of 1-hour TSP
Monitoring Results in the Reporting Period
| 
    Monitoring Station  | 
   
    Average (µg/m3)  | 
   
    Range (µg/m3)  | 
   
    Action Level 
   (µg/m3)  | 
   
    Limit Level  (µg/m3)  | 
  
| 
   DM-1  | 
  
   30  | 
  
   18-47  | 
  
   279  | 
  
   500  | 
 
Major
dust sources in the reporting period included haul road traffic, excavation,
loading and unloading of sand/fill material and filling works under the
Project.  
No
exceedance of Action and Limit Levels was recorded for construction air quality
monitoring in the reporting period.  No action was thus required to be
undertaken in accordance with the Event and Action Plan presented in Annex E4. 
According
to the Updated EM&A Manual of the Project, impact noise monitoring was
conducted once per week during the construction phase of the Project.  The
Action and Limit Level for construction noise of the Project is provided in Table
2.4 below.  
Table 2.4        
Action and Limit Levels for Construction Noise
| 
    Time Period  | 
   
    Action Level  | 
   
    Limit Level  | 
  
| 
   0700 - 1900 hours on normal weekdays  | 
  
   When one documented complaint is
  received  | 
  
   75 dB(A) *  | 
 
Notes: 
Limit
level is exceeded when Leq ≥ 75 dB(A).  If
works are to be carried out during restricted hours, the conditions stipulated
in the construction noise permit issued by the Noise Control Authority have to be followed.
* Reduce to 70 dB (A) for schools and 65 dB (A) during
school examination periods.
Noise
monitoring was performed using sound level meter at the designated monitoring
stations NMS-CA-1A ([3])
([4]) and NMS-CA-4
(Figure 2.2; Table 2.5) in accordance with the
requirements stipulated in the Updated EM&A
Manual.  Acoustic calibrator was deployed to check the sound level
meters at a known sound pressure level.  Details of the deployed equipment
are provided in Table 2.5.  Copies of the calibration certificates
for the equipment are presented in Annex F1.  
Table
2.5         Noise Monitoring Details
| 
    Monitoring Station (a)  | 
   
    Location  | 
   
    Parameter  | 
   
    Frequency and Duration  | 
   
    Monitoring Dates  | 
   
    Equipment  | 
  
| 
   NMS-CA-1A (b)   | 
  
   Residential
  premise in Tung Chung East – Century Link/Ying Hong Road (c)    | 
  
   30-minute measurement between 0700 and
  1900 on normal weekdays (Monday to Saturday). Leq,
  L10 and L90 would be recorded.   | 
  
   Once per week for 30 mins
  during the construction period of the Project  | 
  
   3, 9, 15, 21 and 27 March 2023  | 
  
   Sound Level Meter: Rion NL-52 (S/N:
  00542913)   Acoustic Calibrator: LARSON DAVIS
  CAL200 (S/N: 10227)  | 
 
| 
   NMS-CA-4  | 
  
   Residential
  premise in the reclamation area next to Tung Chung East – Ying Tung Estate    | 
  
      | 
 |||
| 
   Remarks: (a)     
  It should be noted that
  impact monitoring at other construction noise monitoring locations at TCE as
  stated in the Updated EM&A Manual will commence after the flat intake of
  residential premise in TCE (for Monitoring Station NMS-CA-1) and operation of
  schools (for Monitoring Stations NMS-CA-2 and NMS-CA-3). (b)     
  Impact monitoring at monitoring station NMS-CA-1A commenced on 19
  September 2018 in view of the close vicinity of the construction works near
  the residential area at Century Link.  (c)     
  Due to land handover
  issue, NMS-CA-1A was relocated to Ying Hong Road which is located 60m away
  from the original location.  Proposal on the relocation of NMS-CA-1A was
  approved by IEC on 23 November 2018.  Noise monitoring at the relocated
  location commenced since 24 November 2018.  | 
 |||||
The
schedule for noise monitoring during the reporting period is provided in Annex F2.
Results
for noise monitoring are summarized in Table 2.6.  The monitoring
data and the graphical presentation are provided in Annex F3. 
Table
2.6         Summary of Construction
Noise Monitoring Results in the Reporting Period
| 
    Monitoring Station  | 
   
    Average, dB(A), Leq (30mins)  | 
   
    Range, dB(A), Leq (30mins)  | 
   
    Limit Level, dB(A), Leq (30mins)  | 
  
| 
   NMS-CA-1A   | 
  
   66.3  | 
  
   63.2-69.4  | 
  
   75  | 
 
| 
   NMS-CA-4  | 
  
   68.2  | 
  
   66.5-70.8  | 
  
   75  | 
 
Major
noise sources during the noise monitoring included noise from plant operation,
craning, piling, haul road traffic, nearby traffic and
aircraft as well as nearby construction sites.  
No Action/ Limit Level exceedance was
recorded for construction noise monitoring in the reporting period.
Impact
water quality monitoring was carried out to ensure that any deterioration of
water quality was detected, and that timely action was taken to rectify the
situation.  Impact water quality monitoring was undertaken three days per
week since the commencement of marine works during the reporting period in
accordance with the Updated EM&A Manual.  Each impact water quality
monitoring was scheduled such that the interval between two impact water
quality monitoring was more than 36 hours to record representative water
quality data throughout the week during the marine works.
Two (2) replicate in-situ
measurements and samples were collected at each monitored water depth of each
designated monitoring stations.  Dissolved Oxygen (DO), pH value,
salinity, temperature and turbidity were measured in-situ
whereas the level of suspended solids (SS) were determined by ALS Technichem (HK) Pty Ltd which is a HOKLAS accredited
laboratory.
The
Action and Limit Levels of the water quality monitoring are provided in Table
2.7.
Table
2.7         Action and Limit Levels for
Water Quality
| 
    Parameters  | 
   
    Action Level  | 
   
    Limit Level  | 
  
| 
   DO in mg/L  (Surface, Middle & Bottom)  | 
  
   Surface and Middle 5.9 mg/L [1]   Bottom 5.6 mg/L  | 
  
   Surface and Middle 4 mg/L [1]   Bottom 2 mg/L    | 
 
| 
   SS in mg/L (Depth-averaged)  | 
  
   13.5 mg/L      | 
  
   23.5 mg/L  | 
 
| 
   Turbidity in NTU (Depth-averaged)  | 
  
   17.1 NTU  | 
  
   23.5 NTU  | 
 
Notes:
(1)        For DO,
non-compliance occurs when monitoring results is lower than the limits. 
(2)       
For SS and Turbidity, non-compliance occurs when monitoring results is larger
than the limits
The locations of the monitoring
stations under the Project are shown in Figure 2.3 and Table 2.8.
Table
2.8         Locations of Impact Water
Quality Monitoring Stations and the Corresponding Monitoring Requirements
| 
    Monitoring Station  | 
   
    Description  | 
   
    Coordinates  | 
   
    Parameters (a)  | 
   
    Frequency  | 
   
    Monitoring Dates  | 
   
    Depth  | 
  |||
| 
      | 
  
      | 
  
   Easting  | 
  
   Northing  | 
  
      | 
  
      | 
  
      | 
 |||
| 
   TCE-WQM1  | 
  
   Near Airport
  Channel  | 
  
   811838  | 
  
   817341  | 
  
   Ÿ Dissolved
  Oxygen (DO) (mg/L and % saturation) Ÿ Temperature
  (°C) Ÿ Turbidity
  (NTU) Ÿ Salinity
  (ppt) Ÿ pH Ÿ Water
  depth (m) Ÿ Suspended Solid (SS) (mg/L)  | 
  
   Impact monitoring: 3 days per
  week, at mid-flood and mid-ebb tides during the construction period of the
  Project    | 
  
   1,
  3, 6, 8, 10, 13, 15, 17, 20, 22, 24, 27, 29 and 31 March 2023  | 
  
   3
  water depths: 1m below sea surface, mid-depth and 1m above
  seabed.  If the water depth is less than 3m, mid-depth sampling
  only.  If water depth less than 6m, mid-depth may be omitted  | 
 ||
| 
   TCE-WQM2a  | 
  
   Marine Park 1  | 
  
   814439  | 
  
   819879  | 
 ||||||
| 
   TCE-WQM2b  | 
  
   Marine Park 2  | 
  
   814439  | 
  
   821905  | 
 ||||||
| 
   TCE-WQM3A  | 
  
   Outlet of Tai
  Ho Wan  | 
  
   814705  | 
  
   817859  | 
 ||||||
| 
   TCE-WQM4  | 
  
   HKBCF  | 
  
   813344  | 
  
   818849  | 
 ||||||
| 
   TCE-C1  | 
  
   Control
  Station - Outside Airport Channel  | 
  
   804247  | 
  
   815620  | 
 ||||||
| 
   TCE-C2  | 
  
   Control
  Station - Sunny Bay  | 
  
   819460  | 
  
   821473  | 
 ||||||
| 
      | 
  
   Notes:
    | 
 ||||||||
| 
      | 
  
   (a)     In
  addition to the abovementioned parameters, other relevant data shall also be
  recorded, including monitoring location / position, time, water depth, tidal
  stages, weather conditions and any special phenomena or work underway at the
  construction site.   | 
 ||||||||
Table 2.9 summarizes the equipment used in the impact water quality
monitoring works.  Copies of the calibration certificates are attached in Annex G1.
Table
2.9         Water Quality Monitoring
Equipment
| 
    Equipment  | 
   
    Model  | 
  
| 
   Water
  Sampler  | 
  
   Kahlsico Water Samplers  | 
 
| 
   Multi-parameter
  Water Quality System (measurement of DO,
  Temperature, Turbidity, Salinity and pH)  | 
  
   YSI
  ProDSS (S/N: 15M100005, 16H104234, 17E100747 and
  21G105356)   | 
 
| 
      | 
 |
The
schedule for water quality monitoring during the reporting period was provided
in Annex G2.  
A
total of 14 monitoring events for impact water quality monitoring were conducted
at all designated monitoring stations during the reporting period.  Impact
water quality monitoring results and graphical presentations were provided in Annex G3.  
Action
level exceedance was recorded for water quality impact monitoring in the
reporting period and the event and action plan (Annex G4) was
undertaken.  Investigation on the action level exceedance was conducted
and summarized in Table 2.10 below. 
Table
2.10       Details of Exceedances Recorded for
Water Quality Monitoring
| 
   Date  | 
  
   Tide  | 
  
   Parameter  | 
  
   Station  | 
  
   Type  | 
  
   Justification  | 
 |
| 
    24 March 2023  | 
   
    MF  | 
   
    SS  | 
   
    TCE-WQM4  | 
   
    Action  | 
   
    (a) (b)  | 
  |
| 
      Remarks:  | 
  ||||||
| 
    (a)  | 
   
    The exceedance was not considered
   as caused by the construction of the Project due to areas of
   reclamation related marine works undertaken under the Project were
   surrounded by silt curtain which were inspected daily by the Contractor and
   inspected periodically by ER.  The silt curtain nearby the water
   quality monitoring stations was observed to be in good
   condition/well-functioning.  | 
  |||||
| 
    (b)  | 
   
    The exceedance was not considered
   as caused by the construction of the Project due to no illegal
   discharge/sediment plume was observed nearby the water quality monitoring
   station during the sampling in mid-ebb/mid-flood tide.  | 
  |||||
Based
on the investigation conducted for each of
the monitoring day with exceedance, the exceedance of SS was not likely caused
by the work activities related to the Project.  
Nevertheless,
the Contractors were reminded to implement all relevant mitigation measures for
the marine works, including regular checking of silt curtain integrity, provide
periodic maintenance and maintain good site practice.  The ET will keep on
checking monitoring data, plant, equipment and
Contractor’s working methods.  
Compensation
woodland planting under Contract 2 was completed on 30 September 2022. 
Monitoring for compensation woodland will be carried out after the confirmation
of the monitoring proposal.  Photographic record of the compensation
woodland planting is provided in Annex
H.
Plant
species of conservation importance, including three individuals of Aquilaria
sinensis and 33 individuals of Gmelina chinensis, were identified
within works areas for Contract 2.  All individuals of Aquilaria
sinensis and 31 individuals of Gmelina chinensis were recommended
being preserved in-situ while two individuals of Gmelina chinensis
(RT-07 and RT-08) were recommended being transplanted to the receptor site in
accordance with the Detailed Preservation and/or Translocation Plan for Plant
Species of Conservation Importance approved under Condition 2.21 of
EP-519/2016.  Initial tree survey was conducted in September 2021 under
Contract No. NL/2020/02 before the commencement of construction works.  According
to the initial tree survey conducted, the in-situ preserved plant
species of conservation importance of which one individual of Aquilaria
sinensis and six individuals of Gmelina chinensis were found
missing.
Monthly
monitoring of the in-situ preserved plant species of conservation
importance by the Qualified Personnel (QP) appointed under Contract 2 was
implemented in the reporting period.  Health condition was considered fair
for the majority of the in-situ preserved plant
species of conservation importance, of which two individuals of Gmelina
chinensis could not be monitored as a result of unsafe access to the
locations, as recorded during the monitoring carried out on 20 March
2023.  
Tree
protection zones for the in-situ preserved plant species of conservation
importance were demarcated.  No injuries and/or damages to the individuals
of the in-situ preserved plant species of conservation importance were
reported by the QP since the previous monitoring events.  Photographic
record and tree schedule of the preserved plant species of conservation
importance monitoring are provided in Annex I.
The
ET will continue to monitor the implementation of monitoring of in-situ
preserved plant species of conservation importance.
Site
visit to the receptor site for the transplanted plant species of conservation
importance under Contract 2 was carried out on 20 January 2022 prior to the
commencement of transplantation works for the transplanted plant species of
conservation importance on 21 January 2022.  
The
transplanted plant species of conservation importance were both certified as
dead trees by the QP on 15 June 2022 as no living signs were observed.
 Replacement planting of new trees of the same species, or other species
to the satisfaction of the Project Manager, at the Contractors’ expense would
be deemed necessary in accordance with the conditions under the approved
Detailed Preservation and/or Translocation Plan for Plant Species of
Conservation Importance.  Revised replacement planting proposal prepared
by the QP was submitted to EPD.  No further comment from EPD for the
proposal was received and related replacement planting will be proceeded
according to the arrangements specified in the proposal.
Mangrove
eco-shoreline and rocky eco-shoreline are under construction while the
construction of vertical eco-shoreline has been substantially completed. 
Photographic record is provided in Annex J.
No
eco-shoreline monitoring was scheduled during the reporting period. 
Monitoring shall be conducted for at least 3 years after the completion of
reclamation works, twice in wet season and twice in dry season, in order to determine the effectiveness of the eco-shoreline
in accordance with the Updated EM&A Manual.
According
to the Updated EM&A Manual of the Project, impact soft shore ecological
monitoring has to be conducted quarterly at each
survey location at Tung Chung Bay (TCB) and Tai Ho Wan (THW) covering wet and
dry seasons during the marine construction of the Project.  The soft shore
ecological monitoring consisted of qualitative walk-through surveys,
quantitative transect surveys and sedimentation rate monitoring at the
accessible survey locations of TCB and THW.
For
qualitative walk-through surveys, the accessible shoreline of TCB and THW at
each of the three shore heights: 2 m, 1.5 m and 1 m above Chart Datum was surveyed, and organisms encountered were
recorded and their relative abundance noted.  In
particular, active search of horseshoe crabs and seagrasses were
conducted to confirm whether these species are present along the sites.  
For
quantitative transect survey, one 50 – 100 m horizontal (belt) transect (actual
length subject to the site conditions) was surveyed at each of the three shore
heights: 2 m, 1.5 m and 1 m above Chart Datum of each
survey location.  On each transect, five quadrats (50 cm x 50 cm) were
placed randomly in each transect to assess the abundance and distribution of
flora and fauna.  For each quadrat, surface layer to 5 cm depth was sieved
and microbenthic organisms (e.g. crustaceans) were recorded
and identified.  Density of organisms was expressed as individuals / m2. 
Areas with seagrass were also recorded and identified and other information,
such as the percentage cover, were also recorded.  Sessile animals such as
barnacles and oysters in each quadrat were not counted but estimated as
percentage cover on the rock surface.  All species of algae (encrusting,
foliose and filamentous) were also identified and recorded by estimating the
percentage cover on the rock surface.  All organisms were identified to
the lowest possible taxonomic level (at least Genus
level).  Species encountered outside the quadrat but in the vicinity of
survey transect were also recorded.
For
sedimentation rate monitoring, to avoid disturbance to the mudflat and nuisance
to navigation, no fixed marker/monitoring rod was installed at the monitoring
stations.  A high precision Global Navigation Satellite System (GNSS) real
time location fixing system was used to locate the station in the precision of
1 mm, which is reasonable under flat mudflat topography with uneven mudflat
surface only at micro level.    
Measurements
were taken directly on the mudflat surface.  The Real Time Kinematic GNSS
(RTK GNSS) surveying technology was used to measure mudflat surface levels and
3D coordinates of a survey point.  The RTK GNSS survey was calibrated
against a reference station in the field before and after each survey. 
The reference station is a survey control point established by the Lands
Department of the HKSAR Government using professional surveying instruments
such as total station, level and geodetic global
navigation satellite system.  The coordinates system is in HK1980 GRID
system.  The reference station was surveyed and established by traditional
land surveying methods using professional surveying instruments such as total
station, level and geodetic GNSS.  The accuracy was down to mm level and
higher than the proposed RTK GNSS cm level so that the reference control
station has relatively higher accuracy.  As the reference control station
has higher accuracy, it was set as true evaluation relative to the RTK GNSS
measurement.  All position and height correction were adjusted and
corrected to the reference control station.
The
precision of the measured mudflat surface level reading (vertical precision
setting) was within 10 mm (standard deviation) after averaging the valid survey
records of the XYZ HK1980 GRID coordinates.  Each survey record at each
station was computed by averaging at least three measurements that are within the
above specified precision setting.  Both digital data logging and written
records were collected in the field.  Field data on station fixing and
mudflat surface measurement were recorded.  
The
schedule for soft shore ecological monitoring during the reporting period is
provided in Annex K1. 
Impact
soft shore ecological monitoring was conducted at three (3) monitoring
locations at Tung Chung Bay (TCB), situated in the eastern side (TCB1),
southern side (TCB2) and western side (TCB3) as well as one (1) monitoring
location at Tai Ho Wan (THW) as shown in Figure
2.4 during the reporting period.  Representative photographs taken
during the impact monitoring are presented in Figure 2.5.
For
qualitative walk-through surveys, horseshoe crabs and intertidal soft shore
communities were recorded during the impact monitoring.  The survey
results for each monitoring location are summarized in Table 2.11 below
and detailed in Annex K2.
Table 2.11       Summary of Qualitative
Walk-through Surveys
| 
    Location  | 
   
       | 
   
    Horseshoe Crabs  | 
   
    Seagrass  | 
   
    No. of Other Intertidal Species  | 
  ||
| 
    Date and Time (1)  | 
   
    No. of Species  | 
   
    No. of Individuals  | 
   
    No. of Species  | 
   
    Area Coverage (m2)  | 
  ||
| 
   TCB2    | 
  
   10/03/2023  | 
  
   -  | 
  
   -  | 
  
   -  | 
  
   -  | 
  
   35  | 
 
| 
   TCB1    | 
  
   21/03/2023  | 
  
   -  | 
  
   -  | 
  
   -  | 
  
   -  | 
  
   34  | 
 
| 
   THW  | 
  
   23/03/2023  | 
  
   1  | 
  
   6  | 
  
   -  | 
  
   -  | 
  
   37  | 
 
| 
   TCB3    | 
  
   24/03/2023  | 
  
   1  | 
  
   3  | 
  
   1  | 
  
   94    | 
  
   40  | 
 
Note:  
(1)           
Quantitative and qualitative
transect surveys were conducted on 10 March 2023 at TCB2, 21 March 2023 at
TCB1, 23 March 2023 at THW and 24 March 2023 at TCB3.
For
the quantitative transect surveys, a total of 4,977
individuals were recorded from all transects at monitoring stations
TCB1, TCB2, TCB3 and THW.  The most abundant group of intertidal soft
shore communities recorded was gastropods, with a total of 4,811 individuals (relative abundance of 96.7% and density of
320.7 individual m-2).  The summary of the top three dominant
species at each shore height of each monitoring station and the complete list
of species and density recorded are presented in Annex K2.  When
compared with the results obtained during the baseline monitoring as presented
in the Baseline Monitoring Report ([5]),
there was no indication of a change in the composition of intertidal
communities recorded during the reporting period.
The mudflat surface levels at the four
selected monitoring stations in March 2023 and the corresponding XYZ HK1980
GRID coordinates are presented in Table 2.12.  When compared with
the results obtained during the baseline monitoring as presented in the
Baseline Monitoring Report (1),
slight changes with <0.04 mPD of sediment levels
are recorded for the monitoring stations.  The ET will continue to observe
the trend of change in sediment levels over time for further comparison and
review.  
Table
2.12       Results of Sedimentation Rate
Monitoring
| 
    Monitoring
   Station  | 
   
    Northing
   (m)  | 
   
    Easting
   (m)  | 
   
    Z
   level at March 2023 (mPD)
     | 
   
    Remarks  | 
  
| 
   TCB1  | 
  
   816068.677  | 
  
   811129.293  | 
  
   1.288  | 
  
   Soft
  mudflat  | 
 
| 
   TCB2  | 
  
   815812.756  | 
  
   810917.398  | 
  
   1.117  | 
  
   Soft
  mudflat  | 
 
| 
   TCB3  | 
  
   816027.367  | 
  
   810696.222  | 
  
   1.076  | 
  
   Soft
  mudflat  | 
 
| 
   THW  | 
  
   817472.076  | 
  
   815850.327  | 
  
   1.020  | 
  
   Soft
  mudflat  | 
 
Based
on the impact monitoring results, there was no evidence showing any significant
difference in intertidal communities when compared against the data obtained
during baseline monitoring.  No action is thus required to be undertaken
in accordance with the Event and Action Plan presented in Annex K3.  The ET will
continue to observe the change in density or the distribution pattern of
horseshoe crab, seagrass and intertidal soft shore communities taking into account natural fluctuation in respect of the
occurrence and distribution pattern.
Site inspections were carried out
on a weekly basis with the Contractor and ER to monitor the implementation of
proper environmental pollution control and mitigation measures for air quality, noise, water quality,
waste management, marine ecology, landscape and visual impacts and
preservation and/or transplantation of plant species of conservation importance
under the Project.  In the reporting period, five (5) site inspections
were carried out on 2, 9, 16, 23 and 30 March 2023 for Contract 1, five (5)
site inspections were carried out on 1, 8, 15 and 22 and 29 March 2023 for
Contract 2, five (5) site inspections were carried out on 3, 10, 17, 22 and 31
March 2023 for Contract 3 and four (4) site inspections were carried
out on 7, 14, 21 and 28 March 2023 for Contract 7.
Key
observations during the site inspections are summarized in Table 2.13.
Table 2.13      Key Observations Identified during the
Site Inspection in this Reporting Month 
| 
    Contract
   No.  | 
   
   
    Inspection
   Date   | 
   
   
    Environmental
   Observations  | 
   
   
    Recommendations/
   Remarks  | 
   
  
| 
   Contract 1  | 
  
  
   2 March 2023  | 
  
  
   Area E   
  No
  deficiency was observed.  | 
  
  
     
  Nil  | 
  
 
| 
   9 March 2023  | 
  
  
   VS3   
  Appropriate Non-road
  Mobile Machinery (NRMM) label was not observed on generator.  | 
  
  
   VS3   
  The
  Contractor was reminded to affix appropriate NRMM labels in accordance with
  the Air Pollution Control (Non-road Mobile
  Machinery) (Emission) Regulation.  | 
  
 |
| 
   16 March 2023  | 
  
  
   Area E  
  Accumulated
  refuse was observed on ground.  Interim Open Rectangular Channel
  (IORC)  
  Dusty
  haul road was observed.  | 
  
  
   Area E  
  The
  Contractor was reminded to remove the refuse in a timely manner and maintain
  good housekeeping. Interim Open Rectangular Channel
  (IORC)  
  The
  Contractor was reminded to provide dust mitigation measures, such as
  watering.  | 
  
 |
| 
   23 March 2023  | 
  
  
   Area E  
  Accumulated
  refuse was observed on ground.  | 
  
  
   Area E  
  The
  Contractor was reminded to remove the refuse in a timely manner and maintain
  good housekeeping.  | 
  
 |
| 
   30 March 2023  | 
  
  
   Area E  
  No
  deficiency was observed.  | 
  
  
    
  Nil  | 
  
 |
| 
   Contract 2  | 
  
  
   1 March 2023  | 
  
  
   Portion 3   
  No
  record was observed on the wastewater treatment system checklist.   
  Concrete
  spill was observed on haul road. Area 132    
  Stockpile
  of dusty materials was observed not covered.  
  Accumulated
  general refuse was observed.  | 
  
  
   Portion 3   
  The
  Contractor was urged to display proper record on the checklist.   
  The
  Contractor was urged to keep the public road clean. Area 132   
  The
  Contractor was urged to provide mitigation measures, such as covering the
  stockpile of dusty materials with impervious sheeting.  
  The
  Contractor was reminded to remove the refuse in a timely manner and maintain
  good housekeeping.  | 
  
 
| 
   8 March 2023  | 
  
  
   Portion 3   
  No
  record was observed on the wastewater treatment system checklist.   
  Discoloured Non-road Mobile Machinery
  (NRMM) label was observed on generator.  | 
  
  
   Portion 3   
  The
  Contractor was urged to display proper record on the checklist.   
  The
  Contractor was reminded to affix appropriate NRMM labels in accordance with
  the Air Pollution Control (Non-road Mobile
  Machinery) (Emission) Regulation.  | 
  
 |
| 
   15 March 2023  | 
  
  
   TTA    
  Discoloured Non-road Mobile Machinery
  (NRMM) label was observed on generator. Portion 3   
  Accumulated
  general refuse was observed.   
  Construction
  materials were observed placing near to the retained trees and no tree
  protection was observed.  | 
  
  
   TTA   
  The
  Contractor was reminded to affix appropriate NRMM labels in accordance with
  the Air Pollution Control (Non-road Mobile
  Machinery) (Emission) Regulation. Portion 3   
  The
  Contractor was reminded to remove the general refuse in a timely manner and
  maintain good housekeeping.   
  The
  Contractor was reminded to remove the materials and provide tree protection
  for retained trees.  | 
  
 |
| 
   22 March 2023  | 
  
  
   Portion 3   
  Damage
  was observed on retained tree.   
  Chemical
  containers were observed not placing on drip tray.   
  Mud
  trail was observed on haul road.  | 
  
  
   Portion 3   
  The
  Contractor was urged to critically investigate the cause and provide proper
  tree protection.   
  The
  Contractor was urged to place the chemicals on drip tray.   
  The
  Contractor was urged to keep the public road clean.  | 
  
 |
| 
   29 March 2023  | 
  
  
   Portion 3   
  Chemical
  container was observed not placing on drip tray.   
  Mud
  trail was observed on haul road.  | 
  
  
   Portion 3   
  The
  Contractor was urged to place the chemical on drip tray.   
  The
  Contractor was urged to keep the public road clean.  | 
  
 |
| 
   Contract 3  | 
  
  
   3 March 2023  | 
  
  
   Portion 104   
  Chemical
  containers were observed not placing on drip trays.   | 
  
  
   Portion 104   
  The
  Contractor was reminded to place chemical on drip trays.  | 
  
 
| 
   10 March 2023  | 
  
  
   Road L3   
  Stockpile
  of dusty materials was observed not covered. Main haul road   
  Dust
  was observed generated from haul road.  | 
  
  
   Road L3   
  The
  Contractor was urged to provide mitigation measures, such as covering the
  stockpile of dusty materials with impervious sheeting. Main haul road   
  The
  Contractor was reminded to carry out dust mitigation measures, such as
  watering.  | 
  
 |
| 
   17 March 2023  | 
  
  
   TTA, Portion 16B, 104   
  No
  deficiency was observed.   | 
  
  
     
  Nil  | 
  
 |
| 
   22 March 2023  | 
  
  
   TTA, Portion 11, 104   
  No
  deficiency was observed.   | 
  
  
     
  Nil  | 
  
 |
| 
   31 March 2023  | 
  
  
   TTA, Portion 16B, 104   
  No
  deficiency was observed.   | 
  
  
     
  Nil  | 
  
 |
| 
   Contract 7  | 
  
  
   7 March 2023  | 
  
  
   Portion 146   
  Chemical
  containers were observed not placing on drip tray.  | 
  
  
   Portion 146   
  The
  Contractor was reminded to place the chemical containers on drip tray.  | 
  
 
| 
   14 March 2023  | 
  
  
   Portion 146   
  Discoloured Non-road Mobile Machinery
  (NRMM) label was observed on generator.   | 
  
  
   Portion 146   
  The
  Contractor was reminded to affix appropriate NRMM label in accordance with
  the Air Pollution Control (Non-road Mobile
  Machinery) (Emission) Regulation.  | 
  
 |
| 
   21 March 2023  | 
  
  
   Portion 32   
  No
  tree protection was observed for retained tree.  | 
  
  
   Portion 32   
  The
  Contractor was reminded to provide tree protection to retained tree.  | 
  
 |
| 
   28 March 2023  | 
  
  
   Portion 32, 36, 146   
  No
  deficiency was observed.   | 
  
  
     
  Nil  | 
  
 
The Contractors have rectified all of the observations identified during environmental site
inspections in the reporting period.  The Contractors were reminded to implement all
relevant mitigation measures related to construction dust, construction noise,
water quality and waste management outlined in the EIA Report and Updated EM&A
Manual.  
The
Contractors of Contract 1, 2, 3 and 7 have registered as chemical waste
producer.  Sufficient numbers of receptacles were
available for general refuse collection and sorting. 
All
dump trucks engaged on site was equipped with RTTM system during the reporting
period.  The Surveillance Team of the ET conducted regular site inspection
on the dump trucks and their track records.  No illegal dumping and
landfilling of C&D materials was found during the reporting period.
Wastes
generated during this reporting period include mainly non-inert construction
wastes.  Reference has been made to the waste flow tables prepared by the
Contractors.  The quantities of different types of wastes and imported
fill materials are summarised in Table 2.14. 
Table
2.14       Quantities of Different Waste
Generated and Imported Fill Materials 
| 
   Contract
  No.  | 
  
   Month/ Year  | 
  
   Inert C&D Materials (a)  (m3)  | 
  
   Imported Fill (b) (sand)
  (m3)  | 
  
   Imported Fill (c) (public
  fill) (m3)  | 
  
   Inert Construction Waste
  Re-used (d) (m3)  | 
  
   Non-inert Construction Waste
  (e) (m3)  | 
  
   Recyclable Materials (f)
  (kg)  | 
  
   Chemical Wastes (kg)  | 
 ||
| 
      | 
  
      | 
 |||||||||
| 
   TCNTE
  (East)  | 
  
   1
  to 31 Jan 23  | 
  
   6,231.1  | 
  
   0.0  | 
  
   686.0  | 
  
   6,908.9  | 
  
   237.3  | 
  
   0.0  | 
  
   0.0  | 
 ||
| 
   1
  to 28 Feb 23  | 
  
   0.0  | 
  
   0.0  | 
  
   0.0  | 
  
   2,246.0  | 
  
   150.7  | 
  
   0.0  | 
  
   0.0  | 
 |||
| 
      | 
  
   1
  to 31 Mar 23  | 
  
   0.0  | 
  
   0.0  | 
  
   0.0  | 
  
   1,193.0  | 
  
   164.9  | 
  
   0.0  | 
  
   0.0  | 
 ||
| 
   Notes:  | 
  
      | 
  
      | 
 ||||||||
| 
   (a)
  Inert construction wastes include hard rock and large broken concrete, and
  materials disposed as public fill.  | 
 ||||||||||
| 
   (b)
  Imported materials include of sand fill from any source outside of TCNTE.  | 
 ||||||||||
| 
   (c)
  Imported sorted public fill include all G200, G400 and glass gullet (local
  recycling materials) from any source outside of TCNTE.  | 
 ||||||||||
| 
   (d)
  Reuse of inert construction waste generated under the TCNTE contracts. (e)
  Non-inert construction wastes include general refuse disposed at landfill.  | 
 ||||||||||
| 
   (f)
  Recyclable materials include metals, paper, cardboard, plastics
  and others.  | 
 ||||||||||
Implementation
of applicable landscape and visual mitigation measures was monitored in
accordance with the Updated EM&A Manual.  All measures undertaken by
the Contractor during the construction phase and establishment work phase shall
be audited by ET to ensure compliance with the intended aims of the measures. 
The
implementation status of the environmental protection measures is summarized
below in Table 2.15.  Examples of landscape and visual mitigation
measures are presented in Annex
L1.  The monitoring programme for
detailed design, construction and establishment stages is presented in Table
2.16.  Event and Action Plan for Landscape and Visual impacts is
stated in Annex L2.
Table 2.15       Implementation Status of
Landscape and Visual Mitigation Measures
| 
    Landscape
   and Visual Mitigation Measures during Construction  | 
   
    Implementation
   Status  | 
   
    Relevant
   Contract(s) in the Reporting Period  | 
  
| 
   MM1
  – Optimization of Construction Areas & Providing Temporary Landscape on
  Temporary Construction  | 
  
   Implementation
  of the measures were carried out during the detailed design stage of the
  Project.  | 
  
   NA    | 
 
| 
   MM2
  –  Minimize Topographical Changes  | 
  
   Implementation
  of the measures were carried out during the detailed design stage of the
  Project.  | 
  
   NA  | 
 
| 
   MM3
  – Preservation of Potentially Registerable OVTs, Rare and Protective
  Vegetation  | 
  
   Tree
  Protection Specifications were provided in the relevant Contract
  Specifications respectively for implementation by the Contractors under the
  Project.   The
  Contractors submitted Detailed Preservation and/or Translocation Plan for
  Plant Species of Conservation Importance under EP condition 2.21.   The
  Contractors’ performance on the implementation of the tree maintenance and
  protection measures were observed and checked by the ET weekly during
  construction period.  | 
  
   All
  works contracts  | 
 
| 
   MM4 –
  Transplanting of Existing Trees    | 
  
   Tree
  Transplanting Specifications were provided in the relevant Contract
  Specifications respectively for implementation by the Contractors under the
  Project where trees would unavoidably be affected by the construction works.   The
  Contractors submitted Detailed Preservation and/or Translocation Plan for
  Plant Species of Conservation Importance under EP condition 2.21.    The
  transplanted plant species of conservation importance were both certified as
  dead trees by the QP on 15 June 2022 as no living signs were observed.   | 
  
   Contract
  2  | 
 
| 
   MM5 –
  Screen Hoarding    | 
  
   All
  works contracts  | 
 |
| 
   MM6
  – Adopting Non-dredge Method for the Reclamation  | 
  
   Not
  applicable during the reporting period.  | 
  
   NA  | 
 
| 
   MM9
  – Providing Natural Rock Material/ Planting for Artificial Seawall  | 
  
   Rock
  armour reused and construction of eco-shoreline
  (mangrove eco-shoreline, rocky eco-shoreline and
  vertical eco-shoreline) in progress.  The implementation of mitigation
  measures was checked by ET during weekly site inspection. 
  Implementation of the measures by Contractors was observed.  | 
  
   Contract
  1  | 
 
| 
   MM10
  – Compensatory Planting  | 
  
   Not
  applicable during the reporting period.  | 
  
   NA  | 
 
| 
   MM11
  – Woodland Restoration  | 
  
   The
  implementation of mitigation measures was checked by ET during weekly site
  inspection.  Implementation of the measures by Contractors was observed.  | 
  
   Contract
  2  | 
 
| 
   MM12
  – Screen Planting  | 
  
   Not
  applicable during the reporting period.  | 
  
   NA  | 
 
| 
   MM13
  – Roadside Planting  | 
  
   Not
  applicable during the reporting period.  | 
  
   NA  | 
 
| 
   MM14
  – Aesthetic Design of Built Development  | 
  
   Not
  applicable during the reporting period.  | 
  
   NA  | 
 
| 
   MM15
  – Maximise Greening on Structures  | 
  
   Not
  applicable during the reporting period.  | 
  
   NA  | 
 
| 
   MM16
  – Noise Barrier Design  | 
  
   Not
  applicable during the reporting period.  | 
  
   NA  | 
 
| 
   MM18
  – Landscaping on Slopes  | 
  
   Not
  applicable during the reporting period.  | 
  
   NA  | 
 
| 
   MM20
  – Lighting Control  | 
  
   The
  implementation of mitigation measures was checked by ET during weekly site
  inspection.  Implementation of the measures by Contractors was observed.  | 
  
   All
  works contracts  | 
 
 
Table 2.16       Monitoring Programme for
Landscape and Visual
| 
    Stage  | 
   
    Monitoring
   Task  | 
   
    Monitoring
   Report  | 
   
    Form
   of Approval  | 
   
    Frequency  | 
  
| 
   Design  | 
  
   Monitoring
  of design works against the recommendations of the landscape and visual
  impact assessments within the EIA should be undertaken by the Engineer and
  Landscape Architect, to ensure that they fulfil the intentions of the
  mitigation measures.  Any changes to the design, including design
  changes on site should also be checked  | 
  
   Report
  by CEDD / ER confirming that the design conforms to requirements of EP.  | 
  
   Approval
  by Project Proponent  | 
  
   At
  completion of design stage  | 
 
| 
   Construction  | 
  
   Monitoring
  of the contractor’s operations during the construction period.  | 
  
   Report
  on Contractor's compliance by ET  | 
  
   Counter-signature of
  report by IEC  | 
  
   Monthly  | 
 
| 
   Establishment
  Works  | 
  
   Monitoring
  of the planting works during the 24-months Establishment Period after
  completion of the construction works.  | 
  
   Report
  on Contractor's compliance by ET  | 
  
   Counter-signature of
  report by IEC  | 
  
   Bi-monthly  | 
 
 
A
summary of the Environmental Mitigation Implementation Schedule is presented in
Annex B.  The
necessary mitigation measures were implemented properly for the Project.
The monitoring results
for air quality monitoring (1-hour TSP), construction noise monitoring and
water quality impact monitoring complied with the Action/ Limit levels in the
reporting period.  
Cumulative statistics
on exceedances is provided in Annex M.
There
was no notification of summons or prosecution recorded in the reporting
period.  
One (1) environmental complaint related to Contract 1 was received in the reporting period. 
Investigation was conducted for the environmental complaint in accordance with
the complaint handling process as stated in the Complaint Management
Plan.  Environmental complaint in the reporting period is summarized
below.
| 
       | 
   
    Complaint(s)  | 
   
    Investigation/Follow up action(s)  | 
  
| 
   1  | 
  
     Environmental
  complaint related to Contract 1 regarding dust was
  referred by EPD on 20 March 2023.  | 
  
   Based on the information
  provided by the Contractor with confirmation by RSS, sufficient implemented
  mitigation measures were provided, such as regular watering of haul roads and
  site areas, deploying green net to cover stockpile/surcharge and limiting
  traffic speed within site.  With reference to data from weekly air
  quality monitoring, no project related exceedance was recorded.   | 
 
Statistics
on complaints, notifications of summons, successful prosecutions are summarised in Annex M.
Works to be undertaken in the next
monitoring period of April 2023 are summarized in Table 3.1 below,
together with the key issues and the key mitigation measures:
Table
3.1         Major Activities for the
Next Reporting Period
| 
   Activities  | 
  
   Key Issues  | 
  
   Key Mitigation Measures  | 
 
| 
   Contract
  No. NL/2017/03 - Tung Chung New Town Extension –
  Reclamation and Advance Works (Contract 1)  | 
 ||
| 
   Land-based Works  | 
  
      | 
  
      | 
 
| 
   ·        
  Ground investigation works ·        
  Placing of sorted public fill ·        
  Box culvert construction ·        
  Mangrove planting      | 
  
   ·        
  Dust emission ·        
  Handling and storage of
  C&D materials generated from construction activities
   ·        
  Noise from plant
  operation ·        
  Emission of dark smoke
  from PMEs ·        
  Efficiency of wastewater
  and drainage management   | 
  
   ·        
  Good site practices ·        
  Regular water spraying on
  stockpiles, unpaved haul road and land filling area ·        
  Provide tarpaulin sheets
  coverage on stockpiles ·        
  Sorting and reuse of
  C&D materials as far as practicable ·        
  Use of QPME and noise
  barrier/acoustic mat ·        
  Regular maintenance of
  PMEs ·        
  Implementation of
  wastewater and drainage management  | 
 
| 
   Marine-based Works  | 
  
      | 
  
      | 
 
| 
   ·        
  Laying of geotextile for
  seawall construction ·        
  Seawall construction
  (including vertical seawall, sloping seawall & eco-shoreline)  | 
  
   ·        
  Elevation in impact on
  Water Quality due to marine filling works ·        
  Potential surface runoff ·        
  Potential filling
  material drop from barges ·        
  Disturbance to Chinese
  White Dolphin ·        
  Noise from marine vessels
  and plant operation during normal working hours or restricted hours ·        
  Dust emission during
  storage and transfer of sand/ sorted public fill  ·        
  Emission of dark smoke from
  marine vessel      | 
  
   ·        
  Provision of perimeter
  silt curtain  ·        
  Provision of a leading
  seawall of at least 200m before marine filling works ·        
  Regular cleaning of
  accumulated sand/fill materials at the edge of the barges ·        
  Implementation of Dolphin
  Watching for the marine-based works ·        
  Strictly follow
  requirement under CNP for the use of PMEs and works within restricted period  ·        
  Use of acoustic mat and
  other noise mitigation measures when necessary ·        
  Regular maintenance of
  engines and mechanical equipment  | 
 
 
| 
   Contract
  No. NL/2020/02 - Tung Chung New Town Extension – Salt Water
  Supply System (Contract
  2)  | 
 ||
| 
   Land-based Works  | 
  
      | 
  
      | 
 
| 
   ·        
  RC structure of pumping
  station Construction at Portion 6 ·        
  Construction of service
  reservoir and deflector wall, ground investigation works for deflector wall
  and rigid barrier at Portion 3 ·        
  Remedial works for frac
  out and construction of mud pit 2 for HDD works at Portion 3 ·        
  Watermain laying works at
  Portion 3 along Yu Tung Road ·        
  Sheet piling and
  excavation works for ELS, mobilization and set up of tunnel boring machine
  (TBM) for pipe jacking at Portion 3 ·        
  Removal of existing
  watermain at Watermain Subway at Portion 3 ·        
  Road widening at Yi Tung
  Road at Portion 4 ·        
  Watermain laying works
  and ELS for drainage works at Yi Tung Road at Portion 5 ·        
  Trench excavation,
  manhole construction and pipe laying for drainage works at Portion 5A ·        
  Erection and installation
  of precast unit for box culvert at Portion 5B ·        
  Establishment works for
  the compensatory planting at Portion 1 and 2  | 
  
   ·        
  Dust emission ·        
  Handling and storage of
  C&D materials generated from construction activities
   ·        
  Noise from plant
  operation ·        
  Emission of dark smoke
  from PMEs ·        
  Efficiency of wastewater
  and drainage management  ·        
  Tree protection  | 
  
   ·        
  Good site practices ·        
  Regular water spraying on
  stockpiles, unpaved haul road and land filling area ·        
  Provide tarpaulin sheets
  coverage on stockpiles ·        
  Sorting and reuse of
  C&D materials as far as practicable ·        
  Use of QPME and noise
  barrier/acoustic mat ·        
  Regular maintenance of
  PMEs ·        
  Implementation of
  wastewater and drainage management ·        
  Retain and protect all existing trees and vegetation
  within the study area which are not directly affected by the works  | 
 
 
| 
   Contract
  No. NL/2020/03 - Tung Chung New Town Extension – Major Infrastructure Works
  in Tung Chung East (Contract
  3)  | 
 ||
| 
   Land-based Works  | 
  
      | 
  
      | 
 
| 
   ·        
  Excavation and ELS works
  at Portion 104 ·        
  Excavation and ELS works
  at CUT no.1,2 & 3 and supporting building ·        
  Construction works for
  CUT no. 1 structure ·        
  Construction works and
  furniture installation of PM office at WA9 ·        
  Construction works of
  Contractor office at WA6 ·        
  Drainage, Sewerage and
  watermain works at Road L4, L3, L5 and Portion 16 ·        
  DCS works at Road L4 and
  L3. ·        
  Pipe laying works for
  twin rising mains/ watermain laying at Man Tung Road ·        
  Preparation works for
  pipe jacking works at Ying Tung Road ·        
  Preparation works for
  pipe jacking at Yi Tung Road ·        
  Foundation works for
  noise barrier at Portion 11 ·        
  Road widening works at
  Ying Hei Road  | 
  
   ·        
  Dust emission ·        
  Handling and storage of
  C&D materials generated from construction activities
   ·        
  Noise from plant
  operation ·        
  Emission of dark smoke
  from PMEs ·        
  Efficiency of wastewater
  and drainage management  ·        
  Tree protection  | 
  
   ·        
  Good site practices ·        
  Regular water spraying on
  stockpiles, unpaved haul road and land filling area ·        
  Provide tarpaulin sheets
  coverage on stockpiles ·        
  Sorting and reuse of
  C&D materials as far as practicable ·        
  Use of QPME and noise
  barrier/acoustic mat ·        
  Regular maintenance of
  PMEs ·        
  Implementation of
  wastewater and drainage management ·        
  Retain and protect all existing trees and vegetation
  within the study area which are not directly affected by the works  | 
 
 
| 
   Contract
  No. NL/2020/07 - Tung Chung New Town Extension – Tai Ho Interchange (Contract 7)  | 
 ||
| 
   Land-based
  Works  | 
 ||
| 
   ·        
  Open cut excavation and
  pipe laying for rising main and watermain at Portion 146-5 to 146-9 ·        
  Trench excavation, pipe
  piles and pipe laying works at Portions 32 (Sham Shui Kok
  Drive), Portion 34 Phase 1 and Portions 36-38 ·        
  Trench excavation and
  pipe laying works at Portion 32 (Access Road adjacent to MTRC Siu Ho Wan
  Depot) ·        
  WSD Subway DN200
  diversion and DN1200 installation at Portion 35 ·        
  ELS for construction of
  retaining walls FR1 ·        
  ELS works for Pak Mong Subway Extension Phase 1 ·        
  Piling works for Pak Mong Channel Bridge ·        
  G.I. works for retaining
  wall Wall D&E ·        
  Tree felling works at
  Portions 30 and 33 ·        
  Temporary working
  platform at abutment A1b ·        
  Sheetpiling at Casting Yard A2 and A1 Site
  clearance and tidiness         
    | 
  
   ·        
  Dust emission ·        
  Handling and storage of
  C&D materials generated from construction activities
   ·        
  Noise from plant
  operation ·        
  Emission of dark smoke
  from PMEs ·        
  Efficiency of wastewater
  and drainage management ·        
  Tree protection  | 
  
   ·        
  Good site practices ·        
  Regular water spraying on
  stockpiles, unpaved haul road and land filling area ·        
  Provide tarpaulin sheets
  coverage on stockpiles ·        
  Sorting and reuse of
  C&D materials as far as practicable ·        
  Use of QPME and noise
  barrier/acoustic mat ·        
  Regular maintenance of
  PMEs ·        
  Implementation of
  wastewater and drainage management ·        
  Retain and protect all
  existing trees and vegetation within the study area which are not directly
  affected by the works  | 
 
The
ET will keep track on the construction works to confirm compliance of
environmental requirements and the proper implementation of all necessary
mitigation measures.  The ET will also recommend to the Contractors about
the environmental toolbox topics on the abovementioned key issues for the next
reporting period.
The
tentative schedules for environmental monitoring in April 2023 are provided in Annex N.
This EM&A Report presents the
findings of the EM&A activities undertaken for the TCE Project during the
period from 1 to 31 March 2023 in accordance with the Updated EM&A Manual
and the requirements of the Environmental Permit (EP-519/2016).
Air quality (1-hour TSP), noise,
water quality (DO, turbidity and SS) and in-situ
preserved plant species of conservation importance monitoring were
carried out in the reporting period.  
The monitoring results
for air quality monitoring (1-hour TSP) and construction noise monitoring
complied with the Action/ Limit levels in the reporting period.
No Project-related
Action/ Limit level exceedances were recorded for water quality after
investigation.
Mangrove eco-shoreline
and rocky eco-shoreline are under construction while the construction of
vertical eco-shoreline has been substantially completed.
Based
on the monitoring results for soft shore ecological monitoring, there was no
evidence showing any significant change in intertidal communities when compared
against the data obtained during baseline monitoring.  The ET will
continue to observe the change in density or the distribution pattern of
horseshoe crab, seagrass and intertidal soft shore communities taking into account natural fluctuation in respect of the
occurrence and distribution pattern. 
Monitoring
of the in-situ preserved plant species of conservation importance was carried
out in the reporting period.  Revised replacement planting proposal
prepared by the QP was submitted to EPD.  No further comment from EPD for
the proposal was received and related replacement planting will be proceeded
according to the arrangements specified in the proposal.
Environmental
site inspections were carried out during the reporting period. 
Recommendations on remedial actions were given to the Contractors for the
deficiencies identified during the site inspections. 
There
were no notification of summons or prosecution recorded in the reporting
period.  One (1) environmental complaint related to Contract 1 was
received in the reporting period.  Investigation was conducted for the
environmental complaint in accordance with the complaint handling process as stated
in the Complaint Management Plan.
The
ET will keep track on the construction works to confirm compliance of
environmental requirements and the proper implementation of all necessary
mitigation measures. 
([1])
           ERM (2018a).  Updated Environmental
Monitoring and Audit Manual for Tung Chung New Town Extension. Deposited to EPD
under EP-519/2016
([2])
           Arup (2015).  Environmental Impact
Assessment Report for Tung Chung New Town Extension. Deposited to EPD under Register
No. AEIAR-196/2016
([3])
           Impact monitoring
at monitoring station NMS-CA-1A commenced on 19 September 2018 in view of the
close vicinity of the construction works near the residential area at Century
Link.